Launch of Navy's indigenous aircraft carrier by 2013: Antony


NEW DELHI (PTI): Admitting delay in construction of Indian Navy's indigenous aircraft carrier, the government on Wednesday told the Rajya Sabha that the launch of the ship is now expected to take place next year.

In a written reply to the House, Defence Minister A K Antony said, "The complexity of the project and this being the first ship of its kind being built in India, has led to timelines being extended."

As per the phase-I, the first launch of the ship was envisaged in October, 2010, he said.

"However, due to delays in receipt of steel plates and pre-launch equipment like diesel alternators and gearboxes, the launch of the ship is now expected in 2013," Antony said.

The contract for building the first indigenous aircraft carrier for the Indian Navy has been awarded to Cochin Shipyard Limited.

On scheduled delivery of the ship, he said, "Delivery of the ship is currently envisaged in 2018."

In reply to a question on funds for defence schemes, Antony told the House that for 2012-13 Rs 66,032.24 crore has been allocated for the purpose.

Other Related News

India to host conclave of Army chiefs of Indo-Pacific region

The Indian Army will host a two-day conference of Army chiefs of the Indo-Pacific nations on Sept 26 - 27 with an aim to evolve a common strategy to ensure peace, prosperity and stability against the backdrop of growing global concerns over China's increasing military muscle-flexing in the region.

BRAHMOS Missile Systems

Headlines

Brahmand World Defence Update 2023

Brahmand World Defence Update

Image Gallery